Role filled: Managing Director and Construction Director

The Veja Mate Offshore wind park is located approx. 100 km of the German north sea coast and consists of 67 6MW turbines with a combined capacity of 402 MW.

We were early in the project meet with ambitious goals by both the owners and subsequently by the management team which we were part of. The goals was concentrating on early completion balanced against risk and cost.

  • Project delivered power 6 month ahead of original schedule
  • Project management cost reduced by a factor 2 compared to previous industry standard
  • Significant reduction in risk allocations by proactive investment in technical suitable and proven solutions
  • First power produced only 18 month after financial closure